on 04-08-2010 9:39 AM
Is there possibility to have budget quarterly or half yearly to a project in order to restrict purchase requisitions and purchase orders for particular quarter period.
We got 1cr as our annual budget is there possibility where we can divide our budget in four quarters 20, 20, 20, 40 lak each quarter. In first quarter donu2019t want o exceed my orders more thatn20 lak . . . . .
If there is any solution please let me know
Thanks & regards
Hi,
You can follow what Ahmed has suggested. Adding to Ahmed's reply, make sure that you tick the check box for Releases when you set up your budget profile.Availability will come into picture for the released amount only.
Best Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Any report where we can see released budget or released budget by date to a project.
Thanks & regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, you can see only released budget by date to a project using a std SAP report....use CJI8 report, but at the input screen click Menu>Extras>Select Value type...here selecty only value type 45 and uncheck all other value types...now enter your project number and execute the reprot...you will only released budget to the project with date...you will have to change the layout to get your desired fields....
Hi experts,
Thanks for your reply
But still we want have full budgetary control,
So that in future if i want to know at particular period (2010year/1stquarter) how much amount has been released to a project.
EG: in 2011 i want to know how much amount i have released to a project for a period (2010year/1stquarter)
thanks & regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Budget can be provided either overall or anually...no provision for periodic budget....but as an alternative, you can use budget release function....say allocate 1cr as annual budget and then release only 20 for first quarter and then release another 20 for next quarter like that....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.