on 04-08-2010 9:40 AM
Hello,
When a semifinished material is produced and 101 movement is performed, material is located at interim storage type 901.
As each workcenter is responsible of staging material produced on his area, in order to have an accurate control of the materials that are still pending of staging in a workcenter, we want to have a different interim storage type for each workcenter.
How can we achieve that, without using different movements types for each workcenter?
thanks a lot for your help,
Hannover,
Hi
Pls analyse the below mentioned scenario whether its suitable for your business process
In case if you receive a particular material X from work center A and material Y from work center B , that is what i meant to say is if there is a clear demorgation between materials from a particular work center (Material X will be received only from work center A not from any other work center) then you can use the special movement indicator in the material master and in the ref mvt type-WM mvt type linkage you can mention the special mvt indicator for a WM mvt type and assign the relevant storage type in the WM mvt type level config settings
In this case you need to create multiple WM mvt types not ref/IM mvt types and assign different interium storge types to the relevant WM mvt types.
Regards
Amuthan M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.