on 04-08-2010 9:27 AM
Dear Friends,
We Maintained Cost Varient, KP26 also... but planned cost not showing in this particular order.
is there any others settings required.
please advice
Rajesh G
Some things to check..
- Check the Control tab to ensure you have values in the Plan/Actual Cost Variant fields
- Check the costing log in the order to ensure there are no error messages
- Check your operation control key allows costing
PeteA