The problem because MTO material converted to MTS

Dear Friends,

Here we have converted MTO materials to MTS, now some open PR and PO are there for MTO cyle... but now the same material is been given MTS settings, So Kindly tell me what procedure should I follow to mke the requirement qunatity proper in MD04.

Thanks and Regards,

Krishna

Former Member
Former Member replied

Hi

In MRP-4 view give ind.collective requirement field as "2 - collective requirement". Then re run the MRP in MD01 with option delete and recreate. All unfirmed PRs will be deleted and new will be created. If the PR is firmed then it will have to be deleted manually only.