on 04-08-2010 6:51 AM
When transporting the entries for table V_T7XSSSERRES from the SAP GUI Dev System to SAP GUI Test System
The URL of PCD Page on the Resource that is pointing to the Dev PCD will not match that of the test PCD system
ROLES://portal_content/com.xxxxxx/com.xxxxx.Project/com.sap.pct.erp.ess.bp_folder/com.xxxx.pages.fPages/com.sap.pct.erp.ess.pdata (example only)
How do I resolve this issue as my config when testing in Test PCD does not work?
Thanks
WB
Hello,
Even you transport the PCD contents from Dev to QA portal.
So even the PCD maintained in Dev is transported to PCD maintained in QA it shouldn't be a problem.
But if You Dev and Test Client is both belong to the same instance of the server that (connected to same ECC Dev server) it's fine but if Portal QA is different server which is connected to the ECC QA server it doesn't work (u need to transport to ECC QA from ECC Dev).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.