on 04-08-2010 6:51 AM
Dear All,
Actullay In MRP run system is generating 10000 qty in planned order but in MD61 there is only 3000 qty and no sales order requirement also exists for the same. And when i rerun the MRP by choosing option 3 in planning mode, then also it is generating the planned order for 10000 qty only but Iam not able find out the base requirement for that. Kindly suggest me the solutions.
Regards,
Krishna
s
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you check minimum lot size and safety stock?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In MD04 at bottom, you can see a button for pegged requirement, click there you will come to know the list of requirement. It is not only because of Planned independent requirement you maintain in Md61, it could be due to lot size in Material master, or if you have fixed vendor in sourcelist then it could be because of Minimum order quantity with the vendor, or it could be safty stock or reorder point maintained in Material master
Regards
Antony
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.