Regarding FB02 t-code

Former Member
0 Kudos

Hi,

AT THE TIME OF FB02, FOR MIRO POSTED IN CURRENT DATE/YEAR.BASELINE DATE 31.03.2010 WAS ACCEPTED BY SYSTEM.BY THAT PROJECT CHARGES WAS DEBITED IN LAST YEAR GRANT.

What needs to be done in this case?

Accepted Solutions (0)

Answers (1)

Answers (1)

sridevi_p
Active Contributor
0 Kudos

Hi,

Try using validation to restrict baseline date to hold any previious year values.

Regards,

sridevi

Former Member
0 Kudos

Dear Sridevi,

Thats fine of doing the validations but now what needs to be done of the charges that was debited last year