on 04-07-2010 5:50 PM
Hi,
What is the diff between the inhouse production time which is independant and which is dependant on the lot size in the mtl master ? When we transfer the dates from the routing/recipe scheduling which one of the two gets updated ?
Thanks
Hi,
Inhouse time in material master are useful in MRP run.
When you run MRP run systems takes this inhouse time for calculate requirement dates.If you mention inhouse 5 days .In MD61if you keep requirement at 30 Apr.then after MRP run system will show you start date for planned order 25 APR.
Where timings given in routing /recipe are used for schedule the production /process order.
Regards
SANIL.