Maintenance Plan Call object in Past

Hi Experts,

Is it possible to call the object in past in ECC6.0.

Suppose i want to call the PM order in 2008 through sceduling but system is not allowing me.

Is it required any setting in system. i dont want to call it through mannual.

Please tell me is it possible to call the pm order in past through PM Scheduling.

AR

Former Member
Former Member replied

Amit,

It is very much possible to call the object in past from IP10. Only thing you have to ensure is the tasklist attached to maint plan will have to be valid for the past date.

thks