We are on SRM 7.0 ECS, SRM-SUS When i create Service PO in "Required on" and "Confirmed for" i am getting as "TIMEFRAME" instead of the exact date.
When i try to create CONF for Material PO, i get the error "No open or suitable items to create confirmation" and " PO items assigned to other service agent"
Please let me know how to resolve these issues
Regards
Raahul
Hi,
For Question one , please check the PO
If there is no delivery dated filled:
DELIV_DATE 00000000
DELIV_TIME 000000
LEADTIME
VPER_START 00000000 <<<<
VPER_END 00000000
this is the reason why the 2 fields
"Required on"
"Timeframe From" <<<
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rahul,
SRM - SUS scenario does not support the extended classic deployment , so only the process till PO response will work properly.
If you need to support the same , you may have to go in for a consulting solution ,
please see SAP note : 543544 - SUS: Extended Classic Scenario for EBP not supported .
there are many developments needed in confirmaiton and invoice areas to make this work, you could contact the SAP consultants mentioned in the note to be able to get an idea or see how they can implement this solution for you.
you will have to think about how you will keep all 3 system SRM - SUS - ERP in sync for PO, conf , invoice and credit memo documents , so its not a very easy task which can be achieved by configuration alone.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.