How to select a maintenance cycle for a normal correction?

Former Member
0 Kudos

I did tons of testing runs on CHARM.

For u rgent corrections, the CHARM will list all available maintenance cycles for me to choose.

However, for normal corrections seems CHARM assigns the most recently created maintenance cycle automatically.

I believe that there is a way to fix this for normal corrections.

Could some experts kindly share their experience on this?

I appreciate your help.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Could abybody help with this?

Thank you!

RajeevP
Advisor
Advisor
0 Kudos

Hi,

I see some conceptual issues here. for u'gent corrections there is no maintenance cycle related. It has its own task list. For normal correction, there will be only one maintenace cycle in one project. That means, you cannot open 2 maintenance cycle for one project at a time. So your logical component assigned withing the project has only one option to select .

Rajeev

Former Member
0 Kudos

Hi,

In both urgnt and normal correction, the assignment to a maintenance cycle has to be done even if (as Rajeev said) the UC has its own tasklist...

Could you please check that you maintenance cycle is in a relevant phase... If I remember correctly, UC can be attached to a maintenance cycle up to Production phase whereas normal correction have to be attached to the MC before the test phase (included).

Kind regards,

Stéphane.