on 04-06-2010 4:09 PM
Hello
I am migrating some material components to a new project structure.
I have created the new material components and the new PO (based on the old ones) but i do not know now how to link the material component to the PO.Is there any BAPI that does this?
Do i have to first create a purchase requisition for this material component or how can i link the mat component to the PO.
I have used bapi's for creating material components and PO,so i would need also some bapi that could do something like that.
Is there any bapi for changing material component ?
thank you
Hi
before creating material components,we have to set the purchase requisition flag to "immediately" so that a purchase requisition is created immediately after material component creation.
Afterwards i have read the newly created PR's and gave them as parameter to the bapi for PO creation
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.