Dear All.

Question for t.code : V_V2 (rescheduling)

1) When we use t.code for rescheduling (V_V2) , we have found that it is influent on other intercompany p/o schedule line automatically. How to preventing from changing the intercompany p/o schedule line automatically?

2) What is the difference between the result in checking in the field of 'process stock transfer docs' and not checking in the field of 'process stock transfer docs'?

Thank you.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Anybody who can help me ?

Former Member
0 Kudos

Hi

Answer are:

2 - if you don't check process PO then POs will be skipped. As such, whatever date and quantities already confirmed will remain as is.

1. See answer for 2 above.

Frank

Former Member
0 Kudos

Hi Frank,

Thank you for your reply.

Can you provide the way to test it?

Thank you.

Richard

Former Member
0 Kudos

Hi

Just look at the result of V_V2 run itself. I will show you very order it encountered and if it has made any changes, it will display the old qty and date as well as new qty and date. So, if you execute V_V2 without selecting POs, you should not see any POs in your results screen.

Frank

Former Member
0 Kudos

Hi Frank,

Thank you. This helps me a lot.

Now I can check it.