Hi Gurus,

I have been trying to do Mass assignment of Material in Inspection Plan through LSMW but it seems not working.

I have done recording but when Im trying to execute the batch input, I only see one material become assign to inspection plan instead of 4.

Can someone share his thoughts on how to do this?

Thanks,

Raymond

Former Member
replied

Use the page down key during your LSMW recording to get to the bottom of the list to enter a new material assignment. You need enough "page down"'s to know you are always at the bottom of the list. So if you expect to assign 200 materials in a plan, and there is 11 on a screen do 20 page downs first. Then enter the values, save, exi the plan. Repeat for each material to be added.