on 04-05-2010 11:49 AM
hello,
How can i take the project report according to the status.may i know what transaction code to be used.
thanks
sahadev
In Most of PS Structure report you can get the status of PS Object. for whole Proejct use CN41, for only WBS CN43n and so on...
Execute CN43n --> Change Layout and select status, It will give you all user/ System status of that WBS Elements.
If you are asking directly based on status ( dynamic selection / selection ) you want report in PS. I think there is no report for the same.
With Regards
Nitin P.
Edited by: Nitin Patoliya on Apr 5, 2010 5:19 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think you want to run a report and in the input screen you would like to enter status as REL and the system should display all the project with the status REL...If that is what you require...then it is available in std SAP. you need to configure status selection profile in BS42 and in the input screen for project enter * in project definition field and select your status selection profile inside the status button and execute it. You will have your report. But you need to configure the selection profile accordingly.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.