Hi
My client has scenario where finished product is produced from vendor and delivered to customer from vendors place and some components for prodcuing finish product are supplied by client.
My client wants to plan material to be given to vendor for producing finish product.
How to map this scenario
Hi,
Please tell me if i wrong, in case of subcontracting you provide the material to vendor and vendor send the material back to you with providing some operations on the same. In your case the material is not come back.
In that case you will go for some workaround.You can map Third party scenario and for subcontracting you can sale or FOC Sale the material to vendor.
Thanks & Regards,
PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mayuresh,
I also have the similar client requirement.
Can you please inform how did you manage this scenario mapping in scenario.
Your inputs would be really beneficial.
Thanks for your feedback.
Regards,
Pankaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.