Suggesstion on PGI error in VL02n

Former Member
0 Kudos

Dear Experts,

my delivered qyt and picked qty is 10. bu when i do PGI it says

'Delivery has not been completely processed by WM' (overall WM status shows as 'B')

Can you please suggest

Regards

Siva

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Shiva,

The delivey status is B because of your delivery process is integrated with the ware house mangement.

Create the Transfer order using the t. Code LT03

And confirm the Transfer order LT12

or else the picking or packing material also needed to be picked then only your delivery process status will be fully transfered the quantity .

Thanks

Vasu.

Former Member
0 Kudos

Thanks Vasu for timely help. LT12 done and fine now

Regards