Settlement to multiple cost centers

Former Member
0 Kudos

Hi,

I have a function location and the requirement is that whenever an order is created for this function location, the cost of that order should settle to more than one cost center. User should not enter the cost center manually everytime a order gets created.

Please let me know how can I settle a maintenance order to multiple cost center.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Take help of your ABAP team and maintain relation between user and cost center in a customized table. use user exit IWO10027 Generate user-specific settlement rule and check the relation between user and cost center for order.