Sync messages failed due to high load

Former Member
0 Kudos

Hi!

On our test system we had a very high load of async messages for 3 - 4 hours. The async messages were processed successfully but all sync messages failed during this time frame! As soon as the high load of async messages stopped, the sync messages started executing successfully again.

Has anybody also experienced this kind of problem and what can be done to avoid this issue? Thanks for any input and suggestions.

Regards, Tanja

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hey Tanja,

i had a similar issue when testing the box with Load runner, that a simple sync scenario fails when the size of payload or attachment is high, the thing that i did is just increased the virtual memory ,

You can also check the trace files to figure out problem ?

This might not be a definitive answer , hope this helps,

Vara

[PLEASE REWARD FOR POSTING]