lines are not generated for holidays and sundays

Former Member
0 Kudos

Hi

creating a sale order shcedule lines are not generated for sunday for a particular plant .

Schedule lines are generated for subsequent monday only.

the plant calander is also correct

with regards

partha

Accepted Solutions (1)

Accepted Solutions (1)

sidi_reghioui
Active Contributor
0 Kudos

Hi

I would really double check the factory calendar ans the of the plant and sales organisation

regards,

Sidi

Former Member
0 Kudos

Factory calender is correct

and all the days marked as working day

with regards

partha

Former Member
0 Kudos

Thanks to all

resolved self

with regards

partha