There is one SD interview questions related to 'Scheduling', hope kindly help explain, thank you.
Question:
what time will be used in Scheduling...
And please tell how those time are determined or from where is the data source for system could get those time ??
Thank you.
Hello,
1) Backward Scheduling
- Transit time: from the route
- Loading time: from shipping point
- Pick/Pack time: from shipping point
- Transportation planning lead time: from the route
2) Forward Scheduling: if results in a date in the past or material not available at availability date in Backwork Scheduling:
- Use the same time components as in Backwork.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.