Dear experts, with which process do you link posting area 0061 Surcharges for Late Payment and how do you make this link?

Best regards.

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Hi;

It has been used as

Charge (LPC - Late payment Charge) for late items in Invoicing

Charge (LPC - Late payment Charge) for installment plan items in Invoicing

Regards

Shashi

View solution in original post

3 REPLIES 3

Former Member
0 Kudos

Hi;

It has been used as

Charge (LPC - Late payment Charge) for late items in Invoicing

Charge (LPC - Late payment Charge) for installment plan items in Invoicing

Regards

Shashi

0 Kudos

Is there any other customizing point related to LPC??

AmlanBanerjee
Active Contributor
0 Kudos

Hi,

If you want to calculate Interest charge(late payment charge) during-

(a) Dunning- Then use event 0370

(b) Invoicing-Then use event R402