on 03-31-2010 2:16 AM
Dear Experts
Information :
We have DBCI on one physical box & we have another "3" application server on other 3 physicala boxes, and each serve is having around 8 :BGD" work processes. for time being let us name them as "ser1" which is DBCI , "ser2" "ser3" "ser4" Dialog Instances "respectively"
Requiremen:t
When user schedules any job with out Target Server, None of the Background Job should run on Dialog Instance " ser4"
Request
Any Solution / Clue is highly appreciated to realize the requirement
Rgds
Theres a few ways to achieve this...
1.- remove the bgd processes from ser4
2.- select target server for jobs
3.- create a server group in SM61 (you still have to maintain the jobs)
Whats going to be the usage of ser4?
Regards
Juan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Juan...
Thanks ..SM61 ...helped us . We understood by the following note in detail
-
Note 786412 - Determining execution server of jobs w/o target server.
Requirement of Ser4 is...
We have ECC installation on AIX Platform.
Requirement we have to connect to MS-SQL SERVER .
MS-SQL Connection Possible only thru WINDOWS..
When users scheduling Jobs ..the job are failin on WINDOWS Server becuase of " Hetro".
Your SM61 key word given the way to see above Note, and The note was exactly our requirment.
Rgds
PR
User | Count |
---|---|
84 | |
24 | |
11 | |
9 | |
7 | |
6 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.