Dear Experts

Information :

We have DBCI on one physical box & we have another "3" application server on other 3 physicala boxes, and each serve is having around 8 :BGD" work processes. for time being let us name them as "ser1" which is DBCI , "ser2" "ser3" "ser4" Dialog Instances "respectively"

Requiremen:t

When user schedules any job with out Target Server, None of the Background Job should run on Dialog Instance " ser4"

Request

Any Solution / Clue is highly appreciated to realize the requirement

Rgds

Accepted Solutions (1)

Accepted Solutions (1)

JPReyes
Active Contributor
0 Kudos

Theres a few ways to achieve this...

1.- remove the bgd processes from ser4

2.- select target server for jobs

3.- create a server group in SM61 (you still have to maintain the jobs)

Whats going to be the usage of ser4?

Regards

Juan

pr_srinivas
Contributor
0 Kudos

Juan...

Thanks ..SM61 ...helped us . We understood by the following note in detail

-


Note 786412 - Determining execution server of jobs w/o target server.

Requirement of Ser4 is...

We have ECC installation on AIX Platform.

Requirement we have to connect to MS-SQL SERVER .

MS-SQL Connection Possible only thru WINDOWS..

When users scheduling Jobs ..the job are failin on WINDOWS Server becuase of " Hetro".

Your SM61 key word given the way to see above Note, and The note was exactly our requirment.

Rgds

PR