hi sap gurus,
we are configuring STO Process in that we have to create Purhase Order in that there will be pricing related MM & from the reference of Purchase order we will create delivery in sales order. In billing it will take Pricing from Sales order finally.
how it happens.
regards,
balajia
Hi Balaji,
In STO process there will not be any sales order in the picture.
Its purely STO process.
ME21N(PO-UB)->VL10B(PO due for Delivey)->VL02N(PGI)->VF01(Proforma)->MIGO(GR).
With Regards
Azeez.Mohd
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Balaji,
In STO process there will not be any sales order in the picture.
Its purely STO process.
ME21N(PO-UB)->VL10B(PO due for Delivey)->VL02N(PGI)->VF01(Proforma)->MIGO(GR).
With Regards
Azeez.Mohd
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In STO Process, there is no need to create sale order. PO is enough. Follow the steps as already explained.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Follow the following procedure:-
1) first create plant as the customer
2) Then create STPO with PO type as UB
3) Create delivery using t-code VL10D
4) do PGI using t code VL02N . Now the stock will be in transit
5) Then create the proforma invoice with VF01
6) Then do the goods receipt using MIGO at the receiving plant
Regards,
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.