Dear experts

hi,

can we assign a revenue to activity same as WBS ?

thanks indeed

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

No. activities are not billing element

Former Member
0 Kudos

Dear ahmed

Hi

how can i know that one activity has a cost or not? I mean is there any field (such as status) for activity that specify those activities assigned cost. Maybe in activities table.

thanks indeed

Former Member
0 Kudos

At activity level only cost can be planned.

no budget and no revenue can be planned at activity level.

You can check the planned cost in the actvity itself or as a report (check the std reports)

Regards

SURYA

nitin_patoliya
Active Contributor
0 Kudos

For plan cost there any many standard reports in PS. For actaul cost you can give network and activity in CJI3.

With Regards

Nitin P.

former_member203108
Active Contributor
0 Kudos

As Nitin said, you can run reports for cost information on activity. You can use this simple way as well...In Cj20N select the activity for which you want to view cost, then press CtrlF10 and then press CtrlF11 it will show you the cost of that particular activity alone.