Upload Resource Assignement from MS Project to cProjects

Former Member
0 Kudos

HI,

I m having troubles uploading the actual resource linked to a task in MS Project. The role itself is uploaded, the resource assignment is not.

Although I do everything which is required in Note 952180. Using the standard settings in the mapping table, i have filled in an Employee ID in the 'Code' field in the resource view in MS project, this is the HR personnel number which is linked to your Business Partner. I also tried filling in the Business Partner number itself. No assignment is made in both cases....

I am using the standard settings in the mapping table...however there is no mapping rule concerning "Code". Shoudl there be one? I also tried it with including the mapping rule COde - Business Partner number...

Does anyone have an idea on why this is not working properly...

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

this soft is bad for using, if you use OpenPS. I think that it was developed as a hobby and not for real tasks. help is awful.

The best variant for you - use developed Excel template for uploading anything you want to SAP PS.

Former Member
0 Kudos

Hi Bert,

which version of MSP are you using?

thanks

Aravinda

Former Member
0 Kudos

W're using the 4.5 version

Former Member
0 Kudos

no i meant.. MSP 2003 or MSP 2007

Former Member
0 Kudos

o, MSP, using the 2007 standard