Hi Experts,

my Requirement is following this Logic change to extract 12 months of data from consensus planning Book to SCM BI DSOu2019s

Development System already defined in 6 months, but my requirement is we want to change instead of 6 months to 12 months

how to change this logic in Planning Area, please provide me solutions ASAP.

Thanks in Advance

Bye,

Kavitha.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Kavita,

You need to extend plannig bucket profile to 12 months ( from current 6 months) .

This will ensure that you now have 12 months in future , data.

You need to see that Planning area ( at a whole or Key figure level) is intiated for 12 months.

Hope this helps.

Regards

Datta