on 03-25-2010 12:56 PM
Dear Gurus,
I have done GR against Purchase order. Purchase order is having two line items with same material code. For first line item i have cancelled the GR. System has allowed me to cancel GR. My inspection lot is also cancelled . Now i want to cancel GR for second line item also. but the system is giving me error Change the inspection stock in Qm only. What might be the reason?
Regards
Amit
Hi,
Amit for time being remove inspection type 01 from material master & please try .
Once it get reversed again activate it .
Just try I think it will work for you.
Regards
SANIL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Amit,
First check whether you have done GR for second line item and whether inspection lot is generated in QA32.
If the lot is generated then it will be canceled by the same way you have done 1st line Item. Other condition may be somebody might have cleared the lot (Given UD) pertaining to second line item in this case you can't cancel the GR.
Pl check and revert.
Best Regards,
Shekhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check to see if both materials had their stock posted to QI. It could be that one material had the "post to QI stock" turned off in the material master set up for the 01 inspection type.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.