CTP Heuristic using for PIR

former_member309586
Participant
0 Kudos

Hi Gurus,

Can any one explain me How CTP Heuristics can be useful planning trough PIR? at the same time i am not using GATP in APO.

My main thing is i wanted to have finite Heuristic planning run. Please suggest me.

Thanks & Regards,

Raj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Raj,

As you are not using GATP, you cannot succeed in

CTP heuristic without GATP.

In CTP, system carries out the availability check for

the requirements (say sales order) and plans the

missing components.

So, CTP willl not be helpful for you

Regards

R. Senthil Mareeswaran.

Answers (0)