on 03-25-2010 7:28 AM
Hello Experts,
We face a peculiar situation in SRM 4.0 .
While creating SC , when the SCM keeps the SC on hold and make the necessary changes and order the SC .
The followon document is created without approval. We have 1step approval
When i investigate ,
There is no work item triggered for the work flow.
There is no work item in the approval inbox.
But , the status of the SC is showing - Awaiting approval with followon document PR created.
Can you advise on this .
Thanks in advance,
Ram
Hi Ram,
please check in the BBP_PD which workflow was triggered. I suppose that this was the zero step approval, and this is the reason why the follow-on document was automatically created. In this case check/redefine the start conditions in order that
indeed the one-step approval is started.
It's nearly impossible that the SC generates the follow-on document without as the event "setreleased" (which comes from the workflow) triggers the SC transfer.
Regards,
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Peter,
I have checked in BBP_PD . it has triggered the WS10000276 (one - step approval) task .
The workitem number was not generated for this SC , so this was not in approver queue but staus is showing - Awaiting approval with agent assigned and followon document created.
When i checked the same scenario its working fine in Quality system .
This is why i called it as Peculiar situation.
Thanks,
Ram