on 03-25-2010 7:11 AM
Hi;
recently i came up with a problem that i would like to share with you here for any positive feed back on it.
In my scenario i am doing Confirmation on Network Activity, and these activities are lying under a WBS.
Now in one of my WBS i have status PCNF (Partial Confirmation), even though all the Activities lying underneath have status = REL only.
How can i Cancel confirmation on WBS just like Network Activity (CN29)?
Thanks in Advance.
Edited by: e GURU on Mar 25, 2010 8:11 AM
PCNF is set on WBS when you put actaul date on it. For putting actual date on WBS, your required release or Partially released status on all the below activity
Remove actaul date from WBS. PCNF status will be removed by system. You can achieve in most of WBs structure maintenance transaction. But use Cj21 -->Give your WBS --> Enter >Click on Actaul date tab> Click on WBS Element >EDit>WBS--_ Delete -->Delete date.
With Regards
Nitin p.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Nitin;
I dont have any actual dates on my WBS.
Only have Basic dates.
When i try to remove those dates = BLANK, system issues an error message:
System status PCNF is active (WBS N09079.401.191)
Message no. BS013
Diagnosis
Object WBS N09079.401.191 has system status PCNF (Partially confirmed). According to this status, transaction 'Delete basic dates' is not allowed.
@ All
Thank you for your prompt replies.
I am executing confirmation on my Network/Activities.. only
CJEN did not report any thing un-usual, and hence no update on WBS status PCNF (Partial Confirmation)
As per my knowledge system assigns this status as soon as confirmation is been carried out on Activity lying below that WBS.
As Nitin has explained that WBS status PCNF is only set if you enter actual date not basic date and it is canceled if you delete the actual date.
Since your WBS doesn't have actual date but it has status PCNF, maybe you can try to enter any actual date and then delete it, see what happen, if the status PCNF still exists maybe you can contact SAP Global Support
Hope it helps
I think as you have confirmed activity and and again cancelled due to it system has set status PCNF on WBS, I feel that In Latest support pack it shoudld take back PCNF from WBS but it is not taking back in your case. ( recent back in forum we have discussed this thngs with respect to TECO status )
With Regards
Nitin P.
I guess I have the answer, not sure whether it will work for you but its worth trying.
Faced the same issue @ WBS level. Though the Actual dates column was blank, the status was showing PCNF.
I tried CJEN, rebuilding the Database and stuff , but nothing worked. Actually this is how i landed to here searching for similar query.
The Solution that worked for me though is as follows :
I entered a date in Actual Start for WBS and saved the Project (using CJ2B, Planning Board, WBS details)
Then I reopened the project in CJ2B , deleted the Actual Date, and saved it again.
BINGO.... the PCNF Status was gone.
Regards,
MAKAR08
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.