meter reader can not be allocated to a particular MRU for consecutive 3 MR

Former Member
0 Kudos

Hi,

I can plan the meter reader by using EL44 , but one more requirement is there, system should check that one meter reader can not be allocated to a particular MRU for consecutive 3 MR cycle.

Is there any spro setting or standard FM by which I can achive this?

Thanks in advance

2 REPLIES 2

oliviawalsh
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

This functionality is not available in SPRO however....

You may find some of the information in note 1129510 regarding EXIT_SAPLELIN_001 useful to you inorder to implement this.....

I hope this can be of some help.

Regards

Olivia

Former Member
0 Kudos

got ans