Post GR Prior to TO creation in MDE

Former Member
0 Kudos

Hi Gurus,

What are the settings required to post the GR prior to TO creation in Mobile data entry?

Thanks

Sreeni

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member536836
Active Contributor
0 Kudos

Some questions

1.How do you doing goods receipt? Are you scanning SU or HU?

2.Are you creating Inbound delivery ?

Please reply.

Regards,

Prashant

Former Member
0 Kudos

we are using SU, and working with Inbound delivery.

My intention is to Post the GR with reference to Inbound delivery prior to Transfer order.

Sreenivas

Former Member
0 Kudos

It is there under Handling unit configuration . You can tell the system whether TO can be created after the PGR. GOTO-SPRO-Handling unit-Basics-either under warehouse management or Delivery this option is avilable.

Former Member
0 Kudos

Thanks but I tried the same its not working, I dont know what else is missing

Thanks

Srinivas

csaba_szommer
Active Contributor
0 Kudos

The setting is in:

SPRO > Logistics - General > Handling Unit Management > Basics > Delivery > Define Sequence of Transfer order - Goods Receipt

Please check whether HUM requirement is set for the storage location

SPRO > Logistics - General > Handling Unit Management > Basics > Material Management > Inventory Management > HU Requirement for Storage Locations and Default Values for Deliveries

Regards,

Csaba