Hi,
To adjust the duration of a network activity to the maximum delivery time or replenishment lead time of all allocated material components we do in CJ20N: Edit / Component / Transfer delivery time to duration.
Then the ssytem will take
the planned delivery time when the material components are procured externally
the total replenishment lead time when the material components are produced internally or the in-house production time if the total replenishment lead time is not maintained in the material master
--> Can we change the rule to take into account the GR (Quality Control + Warehouse recetion) For exemple by having PDT + GR for material procured externally or to take Total replenishment lead time for both internally and externally procured item?
Thanks in advance for your help,
Chris
From PS you cannot achieve the same. I am not sure But if some way is there in tha case it could be via Material master.chekc along with QM, MM resource
With regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.