on 03-23-2010 9:22 AM
in maintainance of automatic credit control ( t code - ova8 )in dynamic control, horizon period is taken in months, how to change it to weeks or days for maintaining dynamic control
Hi
Kindly check the below
Go to t code OMO1 and select the info structure S066 and click on details and change it day or week
REgards
Damu