Budget Approval Workflow before release.

atul_rajmane
Participant
0 Kudos

Hi,

My Client want to trigger a approval workflow for Budget once its created in CJ30.

Let me know if any once have a worked on same process. Just share a process how we can do it the same.

regards,

Atul R. Rajmane

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member209919
Active Contributor
0 Kudos

Hi,

When project is budgeted in CJ30 status is changed to I0067 (BUDG) you can create a workflow when this status is changed.

Sara

nitin_patoliya
Active Contributor
0 Kudos

Your requirement is not quite clear. Once proejct is created that could be proejct creation approval. Before release of Proejct, If you wanted to approve Proejct budget in that case you can use user status for blocking release of project.

With Regards

Nitin P.

atul_rajmane
Participant
0 Kudos

Hi,

I have created a project in CJ20N. Also, created a cost plan CJ40. Then, I have creted a budget in CJ30. Now, before release of this budget, I need to trigger a approval workflow.

Let me know how we can do this?

regards,

Atul R. Rajmane