Hi Experts,
I was trying to create Appropriation request through IMA11 tcode. In Variants tab, plan values screen area, I am not getting the icon, Create Cost estimate.
Earlier I used to get this icon in the appropriation request, but now it is not appearing, I am not able to understand the reason why? I have checked the customization IMG-INVESTMENT MANAGEMENT - APPROPRIATION REQUEST - PLANNING - COST PLANNING - PROCESS COSTING VARIANT.
Here I have checked the costing variant, we have a Z costing variant, which contains
Costing Type: Approp. Request variant
Valuation Variant: Easy Cost Planning (PS)
This costing variant is assigned to Planning profile and Planning profile is assigned to Appropriation request.
Can some one help me out in solving this issue? Am I missing any other configuration?
Thanks and Regards,
Praveen
I think you are trying to do ECP for APR, if that the case then The appropriation request type has to allow either only projects or only orders as measures. Just check it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.