on 03-22-2010 3:56 PM
Hi
I need to do subcontracting for PM order. I have assinged control key PM02(External opeation) in the operation.
Since it is subcontracting i need to activate the Subcontracing indicator for the opeation. I have double clikced the order and
checked all the tabs but not able to find the indicator..
Please let me know is there any customization setting to activate it??
Regards
S.Senthil
9611811800
You would need Industry solution Discrete Industries and Mill Products (DIMP) SWITCH Activated for this check-box to be visible on the "External" tab of the Operation.
Regards
Narasimhan