on 03-22-2010 11:46 AM
Hi All,
Initially we have implemented the product allocation (ATP) functionality for the regular materials. Now our client wants to have the product allocation functionality for Bill Of Materials (BOM).
I would like to know
1. Whether we can use product alllocation for BOM materials.
2. If yes whether it is possible to do the allocation for both header and sub items.
Regards,
Babs
Please refer to the follwoing notes for more information:
Note 607036
Note 653333
Note 449293
Regards
Sai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use product allocation for the BOM material, this you can do by making the requirement class and schedule line active for PA, associated with the header material. followed by the standard configuration required for PA.
Logically, you should keep the PA active for the header material instead of sub-items. since the Sub items are part of the BOM.
In the item category config you can set the indicator to "A" for "Create delivery group", this will ensure the correct delivery date based on the availibility of both the header and sub-items.
Thanks,
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.