on 03-22-2010 11:24 AM
Hi experts,
I am carrying out cost element planning in CJ40 against one child level wbs (level-2)and
also the cost is flowing from cProject to another child level wbs(level-2).
But after saving the costing data distributed amount at the parenet level WBS should be sum of two individual WBS element cost.
But here in my case , system is showing the cost element data in distributed column and not considering the cost whic flows to costing column and this amount is shown in distributable column.
can anybdy suggest any solutn for the same.
Regards
Ashis
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ashis,
This is the standard behaviour. It is similar you plan costs in PS using easy cost planning. You can see yoou cost total up or in a report or go to CJ20N -->open your project --> SHIFT + F11
Regards,
sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do you see in CJ40 transaction planning from cProjects? Cprojects planning is not integrated.
Regards,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.