wrong values in distributed column in CJ40

Former Member
0 Kudos

Hi experts,

I am carrying out cost element planning in CJ40 against one child level wbs (level-2)and

also the cost is flowing from cProject to another child level wbs(level-2).

But after saving the costing data distributed amount at the parenet level WBS should be sum of two individual WBS element cost.

But here in my case , system is showing the cost element data in distributed column and not considering the cost whic flows to costing column and this amount is shown in distributable column.

can anybdy suggest any solutn for the same.

Regards

Ashis

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

.

former_member209919
Active Contributor
0 Kudos

Hi Ashis,

This is the standard behaviour. It is similar you plan costs in PS using easy cost planning. You can see yoou cost total up or in a report or go to CJ20N -->open your project --> SHIFT + F11

Regards,

sara

former_member209919
Active Contributor
0 Kudos

Hi,

Do you see in CJ40 transaction planning from cProjects? Cprojects planning is not integrated.

Regards,

Sara

Former Member
0 Kudos

i can see cproject cost updated in wbs.....but not included in distributed view of the parent WBS