Carry forward of budget structure in Former budgeting .

Former Member
0 Kudos

Hi,

We are using Former budgeting and we want to carry forward the budget structure(FM9K) to the next fiscal year.Can some one help me in this regard.

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Hello,

You can run the BPCARRY01 program to copy the most recent budget structure to a target year. In doing so, you no longer have to maintain BS elements that already exist.

You execute the program, under Accounting - Public Sector Management - Funds Management - Master Data - Budget Structure - Former Budgeting -Transfer from Previous Year. This is, as Eli said, FM9Z.

Helene

View solution in original post

2 REPLIES 2

iklovski
Active Contributor
0 Kudos

Hi,

I believe, what you need is not FM9K, but FM9Z.

Regards,

Eli

Former Member
0 Kudos

Hello,

You can run the BPCARRY01 program to copy the most recent budget structure to a target year. In doing so, you no longer have to maintain BS elements that already exist.

You execute the program, under Accounting - Public Sector Management - Funds Management - Master Data - Budget Structure - Former Budgeting -Transfer from Previous Year. This is, as Eli said, FM9Z.

Helene