Hi People,
I am running availability check considering replenisehment lead time. Procurement indicator for my material is X( IN house produced and externally procured).
The issue is lets say I enter in house production time as 2 days and GR processing time as 2 days then if today I have zero stock, the system confirms stock after 4 calander working days which is OK. But when I procure material from external vendor and lets say it takes 3 days to procure from him, thinking this I am entering this 3 days value in feild Planned delivery time in MRP 2 view(MARC-PLIFZ). System is not considering this times unless I make procuremetn type as externally produced only.
Am I making any mistake in entering time or by default system will consider time of inhouse production of materila even if procurement type is X.
Please guide?
Hi,
As much as I know, in the standard SAP, when the system is using the RLT it is taking it directly from it's definition in MRP 3 view, field MARC-WZEIT, not by scheduling the LT from other definitions of the material (like you imply).
So, it really doesn't matter if the procurement type is X or else. Check to see if in your system this logic was altered by using a user exit in the ATP check!
Regards,
Mario
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.