on 03-19-2010 1:31 PM
Hello,
I try to adjust the following variant of integration - Single-Object Controlling - Internal Order (Structure Element, manual).
I have the following situation:
1. I have two Internal Orders in ERP with order type CPR1.
2. I have the cProject Project with phases and tasks.
3. I try to assign internal order to cProject project element (in cProject Project - Accounting -> Account Assignment), but to carry out assignment it is not possible.
Error: When I push "Assign" button - "Internal order 6000001 does not exist". But this internal order 6000001 and the second 6000001 are displayed in search result.
Dear colleagues in what there can be problem?
The problem consisted in RFC connection options
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.