I am working on IDOC to file scenario. Do i have to run the idx_noale program at R-3 or PI side? pllease confirm for if it is inbound idoc also?

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos
Former Member
0 Kudos

Hi,

You have to execute this report on PI side.

Or u can also have a look on this blog under-> Switching Off ALE audit messages:

/people/saravanakumar.kuppusamy2/blog/2005/01/20/configuration-tips-for-a-business-serviceintegration-process-to-send-back-ale-audit-idoc

Thank

Amit

Former Member
0 Kudos

I dont want acknoldgements in PI as ack status showing waiting for ack to avoid that i came to know need to run idx_coale report.i want to know where this report needs to run(pi or r-3 side)?

Former Member
0 Kudos

Hi Praveen,

You will need to run this on PI if you want to turn off ALE Acks.....

Hope you know what you need to do, if you don't here is what you need to be doing to turn off ALE Audit

To achieve this add the PORT, CLIENT and MESSAGETYPE of the IDOC to the table IDXNOALE in PI

1.RUN the report IDX_NOALE

2. PORT

3. CLIENT:

4. Exception List: Add Message Type of IDOC

5. Click 'Not Request Acknowledgement'

6. Execute Button.

Verify the table IDXNOALE

1. SE16: IDXNOALE

2. Table should have the change entered.

Try your way around with this method. you'l get what your looking for

Cheers!

Hanish John

shivhare
Active Contributor
0 Kudos

Hi Praveen ,

why you need ack in PI ????

when message successfully posted in ECC you have to get proceeds successful flag in SAP PI .

if any error come in communication channel during message processing then you can configure alert monitoring for communication channel .

Regards,

Amit