Hi Guys,
Is it possible to use SNP PDS with alternate mode for SNP optimizer in SCM 7.0 , If it is not possible then how to create many SNP PDS if there are alternate resources assigned for the product.
Thanks and regards
Thamizh
Hi Thamizh
You can not create SNP PDS for alternate mode.
You need to create different production version for alternate Mode. Only that way you can send SNP PDS.
Regards,
Hitesh