Hi,
This is the question regarding the Transferring the demand planning from SAP APO DP to SAP R/3 .How can we transfer data with the the help of transfer profile .In R/3 where we can see the results?
Thanks
prasanna
Hi Prasanna,
Please follow the below steps
1) Create an activity using transaction /sapapo/mc8t (with
R/3 transfer profile)
2) Create a demand planning job using transaction /sapapo/mc8d
3) Schedule a job using transaction /sapapo/mc8g
4) Execute this job and check the job status in sm37
5) Check the logs under /sapapo/mc8k
In R/3 you can use md74 transaction to check whether the
demand has been transferrred or not.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasanna,
Please confirm whether your query is resolved
Regards
R. Senthil mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.