on 03-17-2010 8:48 AM
Dear All
in my project Process i had created Timesheet entry in cat2 with reference to the WBS element is receiver cost object.Then i tried to transfer to Projectsystem in tcode cat5 the system shows no data transfer to PS Please tell me i need to do any setting for transfer cost from HR to PS?
Regards
Raj
You are using wronge Tcode. As your cost object is WBS in that case you should use T code as CAT7 ( Time transfer to controlling) , After CAT7 you will able to see actual cost on WBS Element.
CAT5 is used when you are using Network activity as cost objectm for the same flow is diff.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is solved by answer given by Mr.Nitin.p
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.