Hi Experts,
Could some one can through ligh on the tolerance keys in SRM.
If we maintain the tolerancce keys for GR in SRM, will it over write the tolerance limits that are maintained in R/3
Appreciate u inputs.
Regards,
Chota Prasad
Hi Chota ,
In SRM the check happens in
read tolerance key customizing table
CALL FUNCTION 'BBP_TOLERANCE_READ_SINGLE'
EXPORTING
i_tol_group = i_tol_group = CT
i_tol_key = i_tol_key = DQ
Please check Table BBP_TOLERANCE , if the CT DQ are mentained correctly.
Summer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
The tolerance keys in SRM will come into picture only for local documents ( GRs and invoices).
So even if no tolerance keys are there in SRM,When the GR or Invoice is replicated to backend , if it fails the tolerance check in backend it will be in 'Error in Process' status.
However this is my understanding.
Regards
Kedar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.