Multiple Appropriation Requests (AR) in single Project Possible?

Former Member
0 Kudos

Dear Experts,

Can we have Multiple Appropriation Requests (AR) in single Project?

i.e. Multiple ARs giving data (plan cost,etc) to create different WBS elements in one Project?

SSanjay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Got Answer:

It's possible.

Multiple ARs to Multiple WBS in single project is possible, but only for TOP WBS Elements.