on 03-15-2010 5:19 PM
Hi,
There is a business requirement to create a simulation basing on a snapshot.
As far as I know it is not possible in standard. Is there some easy way to achieve
that functionality? Otherwise a lot of coding needed?
Thank you.
The only way I could think of without custom development would be to open up the snapshot, export to MS Project and import it back (obviously as a simulation).
Edited by: Lashan Wanigatunga on Mar 16, 2010 2:21 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Since the title states the question the otherway around and the topic is interessting for my problem i'm posting a question in this existing thread.
Is it possible to create a snapshot from a simulation?
The bussines requires the option to validate a simulation. Since a simulation can be changed we would like to take a snapshot from the simulation, use the snapshot as validation and if necessary implement the business requirements back into a new simulation version.
If making a snapshot from a simulation is not possbile, do you have any other solutions to have a non changable version of a simulation?
thanks a lot in advance
Bram
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.